Poland is preparing an auction-based support system for biomethane plants above 1 MW, giving investors a more predictable basis for financing new facilities. Gas distributor Polska Spółka Gazownictwa has issued 495 grid-connection conditions, while energy officials see agricultural waste as a domestic fuel source that could reduce dependence on imported gas.
The renewable energy law amendment was signed by President Karol Nawrocki on 15 October 2026. The provisions governing biomethane auctions are scheduled to take effect on 17 February 2027. The first auction will also depend on European Commission approval of the state-aid arrangements, according to Newseria’s report.
Energy Minister Miłosz Motyka said the government wants to encourage companies under its influence to invest in biogas and biomethane, particularly close to agricultural production. He sees the sector as a way to diversify supplies and ease price pressure, although those outcomes depend on projects being delivered.
Large resource potential, smaller practical opportunity
The National Energy and Climate Plan puts Poland’s technical potential for producing biomethane from waste feedstocks at 8 billion cubic metres. The potential that could realistically be deployed is lower, at 4.7 billion cubic metres, reflecting the size and geographical dispersion of feedstock sources.
In municipalities with the greatest concentration of feedstock, the investment potential is estimated at around 3.2 billion cubic metres. Motyka said adding 3–4 billion cubic metres to the gas system over the coming years would be significant.
On 27 October, Enea and Krajowa Grupa Spożywcza launched cooperation on a potential portfolio of biomethane facilities with combined installed capacity of around 60 MW. The initial work includes feasibility studies for six locations at KGS sugar plants.
Maciej Hodorowicz, deputy director for oil and gas technology at the Oil and Gas Institute, said Poland’s large agricultural sector generates substantial quantities of material that could be used more effectively. Slurry, manure and residues from crop production are among the possible feedstocks.
Connection requests exceed the number of operating plants
PSG reports a marked increase in investor interest over the past two years. Alongside the 495 connection conditions issued, it has two operating biomethane plants connected to its network, 25 agreements under implementation and 42 in preparation.
Chief executive Szymon Paweł Moś told Newseria that more than 2,000 entities had expressed interest. Eight agreements have implementation dates in 2027, although completion will depend on the producers proceeding with their investments.
At the end of September, Poland’s first agricultural biomethane plant connected to PSG’s distribution network opened in Komorów. Its operator, Agro-Biogas, was established by three farmers whose combined operations cover 450 hectares and include 1,600 dairy cows.
Construction began in March 2025, with technical commissioning in August 2026. Before building started, the project required three years of preparations, consultations and permits.
Support aims to improve financing conditions
Moś said the lack of a support mechanism had made innovative biomethane projects difficult to finance. The new auction system is intended to give larger installations more predictable revenue conditions and make it easier to raise investment funding.
PSG is also changing its approach to assessing how much biomethane local networks can absorb. Grid capacity is one part of the challenge; another is public understanding and acceptance of proposed facilities.
Hodorowicz argued that domestic biomethane could strengthen energy security by reducing exposure to disruptions in external gas supplies. The National Energy and Climate Plan’s accelerated-transition scenario envisages Poland’s net energy imports falling from more than 45 million tonnes of oil equivalent in 2020 to around 33 million in 2040, a reduction of approximately 27%. A less ambitious scenario projects a decline of 11%, to around 41 million.
Further changes remain under discussion
Motyka said discussions with the climate ministry cover extending simplified environmental procedures to biomethane plants above 0.5 MW and up to 1 MW. He also raised the possibility of participation mechanisms for local communities, drawing on arrangements used for onshore wind.
These are proposals rather than completed changes. The minister also offered administrative support for expert meetings with residents, saying local governments need help explaining the financial, environmental and energy implications of new projects.
Source: Newseria, 30 October 2026; Ministry of Climate and Environment; Act of 4 September 2026 amending the Renewable Energy Sources Act, Journal of Laws 2026, item 1347.